2023-027 & 028 RFP – (TERM) Bid Packages #5B & #5C #14772
Status
Bidding Closed
Prebid Date12/19/23 2:00pm
Bid Date12/21/23 2:00pm
Sealed bids will be received by JESCO, Inc. Construction, 2211 Michigan Ave., Mobile, AL 36615, until 2:00 PM local
time, December 21, 2023, for the furnishing of all labor and materials and performing all work for constructing the
following contract:
Project No. FSB2021-531-01 BP#5B
Bid Package #5B – Terminal Building Structural Steel Framing
at Mobile International Airport
Mobile, Alabama
The scope of this package shall include the Structural Steel Framing for the following structural components:
1. Provide steel detailing and fabrication of Terminal Structural Steel.
2. Utilize the preliminary wide flange members procured under Bid Package #5 – Steel Mill Order, based on the
Mill Order List procured in the documents.
3. Provide all other steel fabrications required for a complete structural framing system to include the following,
but not limited to,
a. Wind Columns
b. Bracing
c. Curtainwall Support
d. Miscellaneous Fabrications
e. Edge Angles
f. Kickers
g. Framed Openings
h. Floor Deck
i. Roof Deck
j. Accessories
At the specified time, all bids will be publicly opened and read aloud and then evaluated in a private setting. Upon
selection, the CMAR will notify each bidder with the results of the selection.
A pre-bid meeting will be held at Tuesday, December 19, 2023 @ 2:00 PM local time at JESCO, Inc. Field Office,
2211 Michigan Ave., Mobile, AL 36615 for the purpose of briefing prospective bidders, MBE's, and DBE’s about this
project. All prospective bidders are urged to attend.
Major items of work include Bid Package #5B – Terminal Building Structural Steel Framing, Pile Caps, Grade
Beams, and Structural Slab at the Mobile International Airport.
Liquidated Damages for this project shall be 6% annum of original contract per Calendar Day.
A Minority Business Enterprise and Disadvantage Business Enterprise (MBE & DBE) goal of 12.68% has been
established for this project. The Owner’s award of this contract is conditioned upon Bidder or Offeror satisfying the good
faith effort requirements of 49 CFR §26.53. As a condition of bid responsiveness, the Bidder or Offeror must submit the
following information with their proposal on the forms provided herein:
(1) The names and addresses of Minority Business Enterprise (MBE) and Disadvantage
Business Enterprise (DBE) firms that will participate in the contract.
(2) A description of the work that each MBE and DBE firm will perform.
(3) The dollar amount of the participation of each MBE and DBE firm listed under (1)
(4) Written statement from Bidder or Offeror that attests their commitment to use the MBE and
DBE firm(s) listed under item (1) to meet the Owner’s project goal.
(5) If Bidder or Offeror cannot meet the advertised project MBE and DBE goals; evidence of
good faith efforts undertaken by the Bidder or Offeror as described in appendix A to 49
CFR Part 26. Per 49 CFR Part 26.53(b)(3), the Bidder may submit evidence of a good faith
effort within five (5) days after the bid opening.
(6) Written confirmation from each listed MBE and DBE firms that is participating in the
contract in the kind and amount of work provided in the prime contractor’s commitment.
Plans and specifications may be inspected at no charge online at https://www.mobileairportauthority.com/downtown/rfp/.
All prospective bidders MUST notify the CMAR of their intention to bid on the project a minimum of 72 hours before
the time specified for receiving of bids. Bids must be submitted on the forms included within the contract documents
and specifications. Bids shall include all pages included in Division I – Bid Documents. All bid packages should
include two (2) complete sets of the bid documents. Submission of the entire contract book is not required.
Guarantee of Bid IS NOT required.
No bids will be considered unless the bidder, whether resident or non-resident of Alabama, is properly qualified with the
State of Alabama. In addition, non-residents of the State, if a corporation, shall show evidence of having qualified with
the Secretary of State to do business in Alabama.
No contract will be awarded unless the contractor holds a current and appropriate license from the State Licensing Board
for General Contractors, Montgomery, Alabama.
No bid shall be withdrawn for a period of 60 days subsequent to the opening of bids without the consent of the Owner.
MAA reserves the right to reject any and all proposals submitted; to select one or more responding parties; to void this
RFP and the review process and/or terminate negotiations at any time; to select separate responding parties for various
components of the scope of services; and to select a final party/parties from among the proposals received in response to
this RFP. Additionally, any and all RFP project elements, requirements and schedules are subject to change and
modification. MAA also reserves the unqualified right to modify, suspend, or terminate at its sole discretion any and all
aspects of this RFP process, to obtain further information from any and all responding parties, and to waive any defects
as to form or content of the RFP or any responses by any party.
This RFP does not commit MAA to award a contract, defray any costs incurred in the preparation of a response to this
RFP, or contract for any services. All submitted responses to this RFP become the property of MAA as public records.
All proposals may be subject to public review, on request, unless exempted as discussed elsewhere in this RFP.
By accepting this RFP and/or submitting a proposal in response thereto, each responding party agrees for itself, its
successors and assigns, to hold MAA and its agents, directors, consultants, attorneys, officers, and employees harmless
from and against any and all claims and demands of whatever nature or type, which any such responding company, its
representatives, agents, contractors, successors or assigns may have against any of them as a result of issuing this RFP,
revising this RFP, conducting the selection process and making a final recommendation, selecting a responding
party/parties or negotiating or executing an agreement incorporating the commitments of the selected responding party.
By submitting responses, each responding party acknowledges having read this RFP in its entirety and agrees to all
terms and conditions set out in this RFP.
Prospective bidders must obtain the plans and specifications from the CMAR in order to submit a proposal. Request for
plans and specification shall be sent via email to the following email address no later than 72 hours prior to the time of
receiving bids specified: jbuckner@jescoinc.net
Brian Slaughter, Project Director
JESCO, Inc. Construction
Mobile, Alabama
INVITATION FOR BIDS
Sealed bids will be received by JESCO, Inc. Construction, 2211 Michigan Ave., Mobile, AL 36615, until 2:00PM local
time, December 21, 2023, for the furnishing of all labor and materials and performing all work for constructing the
following contract:
Project No. FSB2021-531-01 BP#5C
Bid Package #5C – Central Utility Plant Structural Steel Framing
at Mobile International Airport
Mobile, Alabama
The scope of this package shall include the Structural Steel Framing for the following structural components:
1. Provide steel detailing and fabrication of Central Utility Plant Structural Steel.
2. Utilize the preliminary wide flange members procured under Bid Package #5 – Steel Mill Order, based on the
Mill Order List procured in the documents.
3. Provide all other steel fabrications required for a complete structural framing system to include the following,
but not limited to,
a. Wind Columns
b. Bracing
c. Miscellaneous Fabrications
d. Edge Angles
e. Kickers
f. Framed Openings
g. Floor Deck
h. Roof Deck
i. Accessories
At the specified time, all bids will be publicly opened and read aloud and then evaluated in a private setting. Upon
selection, the CMAR will notify each bidder with the results of the selection.
A pre-bid meeting will be held at Tuesday, December 19, 2023 @ 2:00 PM local time at JESCO, Inc. Field Office,
2211 Michigan Ave., Mobile, AL 36615 for the purpose of briefing prospective bidders, MBE's, and DBE’s about this
project. All prospective bidders are urged to attend.
Major items of work include Bid Package #5C – Central Utility Plant Structural Steel Framing at the Mobile
International Airport.
Liquidated Damages for this project shall be 6% annum of original contract per Calendar Day.
A Minority Business Enterprise and Disadvantage Business Enterprise (MBE & DBE) goal of 12.68% has been
established for this project. The Owner’s award of this contract is conditioned upon Bidder or Offeror satisfying the good
faith effort requirements of 49 CFR §26.53. As a condition of bid responsiveness, the Bidder or Offeror must submit the
following information with their proposal on the forms provided herein:
(1) The names and addresses of Minority Business Enterprise (MBE) and Disadvantage
Business Enterprise (DBE) firms that will participate in the contract.
(2) A description of the work that each MBE and DBE firm will perform.
(3) The dollar amount of the participation of each MBE and DBE firm listed under (1)
(4) Written statement from Bidder or Offeror that attests their commitment to use the MBE and
DBE firm(s) listed under item (1) to meet the Owner’s project goal.
(5) If Bidder or Offeror cannot meet the advertised project MBE and DBE goals; evidence of
good faith efforts undertaken by the Bidder or Offeror as described in appendix A to 49
CFR Part 26. Per 49 CFR Part 26.53(b)(3), the Bidder may submit evidence of a good faith
effort within five (5) days after the bid opening.
(6) Written confirmation from each listed MBE and DBE firms that is participating in the
contract in the kind and amount of work provided in the prime contractor’s commitment.
Plans and specifications may be inspected at no charge online at https://www.mobileairportauthority.com/downtown/rfp/.
All prospective bidders MUST notify the CMAR of their intention to bid on the project a minimum of 72 hours before
the time specified for receiving of bids. Bids must be submitted on the forms included within the contract documents
and specifications. Bids shall include all pages included in Division I – Bid Documents. All bid packages should
include two (2) complete sets of the bid documents. Submission of the entire contract book is not required.
Guarantee of Bid IS NOT required.
No bids will be considered unless the bidder, whether resident or non-resident of Alabama, is properly qualified with the
State of Alabama. In addition, non-residents of the State, if a corporation, shall show evidence of having qualified with
the Secretary of State to do business in Alabama.
No contract will be awarded unless the contractor holds a current and appropriate license from the State Licensing Board
for General Contractors, Montgomery, Alabama.
No bid shall be withdrawn for a period of 60 days subsequent to the opening of bids without the consent of the Owner.
MAA reserves the right to reject any and all proposals submitted; to select one or more responding parties; to void this
RFP and the review process and/or terminate negotiations at any time; to select separate responding parties for various
components of the scope of services; and to select a final party/parties from among the proposals received in response to
this RFP. Additionally, any and all RFP project elements, requirements and schedules are subject to change and
modification. MAA also reserves the unqualified right to modify, suspend, or terminate at its sole discretion any and all
aspects of this RFP process, to obtain further information from any and all responding parties, and to waive any defects
as to form or content of the RFP or any responses by any party.
This RFP does not commit MAA to award a contract, defray any costs incurred in the preparation of a response to this
RFP, or contract for any services. All submitted responses to this RFP become the property of MAA as public records.
All proposals may be subject to public review, on request, unless exempted as discussed elsewhere in this RFP.
By accepting this RFP and/or submitting a proposal in response thereto, each responding party agrees for itself, its
successors and assigns, to hold MAA and its agents, directors, consultants, attorneys, officers, and employees harmless
from and against any and all claims and demands of whatever nature or type, which any such responding company, its
representatives, agents, contractors, successors or assigns may have against any of them as a result of issuing this RFP,
revising this RFP, conducting the selection process and making a final recommendation, selecting a responding
party/parties or negotiating or executing an agreement incorporating the commitments of the selected responding party.
By submitting responses, each responding party acknowledges having read this RFP in its entirety and agrees to all
terms and conditions set out in this RFP.
Prospective bidders must obtain the plans and specifications from the CMAR in order to submit a proposal. Request for
plans and specification shall be sent via email to the following email address no later than 72 hours prior to the time of
receiving bids specified: jbuckner@jescoinc.net
Brian Slaughter, Project Director
JESCO, Inc. Construction
Mobile, Alabama